Data:
2025
C1 Hall Floresti, Cluj County
Project: CONSTRUCTION OF 4 HALLS FOR THE PRODUCTION OF METAL CONFECTIONS AND STORAGE OF FINISHED PRODUCTS / SHOWROOM / TRADE AND RELATED ANNEXES IN 4 STAGES, LANDSCAPING, ACCESS ROADS, FENCING, CONNECTIONS AND CONNECTIONS TO UTILITIES
Client: SC. ASTORIA FINANCING S.R.L.
Technical details and dimensions
The building has a ground floor with partial storey and is built on a solid metal structure, treated anti-corrosive. The external closures are made of sandwich panels, providing optimal thermal and sound insulation. The floor is made of helicopter reinforced concrete, ensuring durability and resistance.
Structure and materials
Main structure: S355J2G3 steel.
Flooring: reinforced concrete, helicopter finish.
Roof and walls: sandwich panels for energy efficiency, 100 mm - roof & 80 mm walls
Finishes and aesthetics
Modern design, with advanced stormwater management systems and perimeter protection sidewalks. The exterior walls are colored in shades of light and dark gray, giving the building a contemporary and professional look.
Finishing process